v3.24.1.u1
Leases (Tables)
3 Months Ended
Mar. 31, 2024
Leases [Abstract]  
Schedule of Lease Costs
The components of lease cost related to the Company's operating leases included in the condensed consolidated statements of operations were as follows:
Three Months Ended March 31,
20242023
(in thousands)
Operating lease cost$11,863 $11,061 
Total lease cost$11,863 $11,061 
Schedule of Lease Liability Maturities
Maturities of the operating lease liabilities as of March 31, 2024 are as follows:
March 31, 2024
(in thousands)
2024 (remaining nine months)$35,076 
202536,932 
202632,522 
202728,004 
202815,804 
Thereafter22,289 
Total lease payments$170,627 
Less: Imputed interest$(18,337)
Total operating lease liabilities$152,290