2023 Restructuring Plan
During 2023, the Company incurred $26 million of restructuring charges. These actions were primarily focused on enhancing organizational efficiency and rationalizing operations. These charges included personnel-related costs resulting from a reduction of approximately 250 employees and other expenses. As part of this restructuring plan, the Company decided to decrease its facilities by closing its owned office in Indianapolis, Indiana, and exiting other leased locations. The 2023 restructuring plan charges consisted of (i) $11 million of personnel-related costs at the Travel and Membership segment, (ii) $9 million of personnel-related costs and $1 million of lease costs at the Vacation Ownership segment, and (iii) $5 million of personnel-related costs at the Company’s corporate operations. These restructuring charges included $2 million of accelerated stock-based compensation expense, which is included within Additional paid-in capital on the Condensed Consolidated Balance Sheets. All material initiative and related expenses have been incurred as of December 31, 2023. As of December 31, 2023, this restructuring liability was $15 million. This liability was reduced by $11 million of cash payments during the six months ended June 30, 2024. The remaining 2023 restructuring liability of $4 million is expected to be paid by the end of 2025.
The Company has additional restructuring plans which were implemented prior to 2023. As of December 31, 2023, the restructuring liability related to these plans was $18 million. This liability was reduced by $3 million of cash payments during the six months ended June 30, 2024. The remaining liability of $15 million, most of which is related to leased facilities, is expected to be paid by the end of 2029.
The activity associated with the Company’s restructuring plans is summarized as follows (in millions):
Liability as ofLiability as of
December 31, 2023Costs RecognizedCash PaymentsJune 30,
2024
Facility-related$17 $— $(2)$15 
Personnel-related16 — (12)4 
$33 $— $(14)$19