v3.25.3
Commitments and Contingencies (Tables)
12 Months Ended
Jun. 30, 2025
Other provisions, contingent liabilities and contingent assets [Abstract]  
Disclosure of Capital Commitments Commitments and guarantees
SA Rand
Figures in million
2025
2024
Capital expenditure commitments
Contracts for capital expenditure (a)
4 316
1 681
Share of joint operation's contracts for capital expenditure
13
21
Authorised by the directors but not contracted for (b)
18 462
14 442
Total capital commitments
22 791
16 144
(a)The increase relates mainly to capital commitments of approximately R1.8 billion for the Eva Copper mine in anticipation
of its start. Further, approximately R0.6 billion of the increase relates to the renewable energy project at Moab Khotsong. 
(b)The increase relates mainly to reclamation and deposition projects and the Nooitgedacht TSF construction project,
increasing approximately R2.1 billion and R1.2 billion respectively. Further to this is approximately R1.6 billion for the
Mponeng life of mine extension and deepening project. This was partially offset by a R0.8 billion decrease for the
Kareerand TSF extension as the project comes to an end in FY26.
Disclosure of Guarantees
SA Rand
Figures in million
2025
2024
Guarantees
Guarantees and suretyships1
757
519
Environmental guarantees2
539
509
Total guarantees
1 296
1 028
1The guarantees and suretyships mainly relate to Eskom guarantees.
2At 30 June 2025, R257 million (2024: R217 million) has been pledged as collateral for environmental guarantees in favour of certain financial institutions.
Refer to note 15.