Commitments and Contingencies (Tables) |
12 Months Ended | ||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Jun. 30, 2025 | |||||||||||||||||||||||||
| Other provisions, contingent liabilities and contingent assets [Abstract] | |||||||||||||||||||||||||
| Disclosure of Capital Commitments | Commitments and guarantees
(a)The increase relates mainly to capital commitments of approximately R1.8 billion for the Eva Copper mine in anticipation of its start. Further, approximately R0.6 billion of the increase relates to the renewable energy project at Moab Khotsong. (b)The increase relates mainly to reclamation and deposition projects and the Nooitgedacht TSF construction project, increasing approximately R2.1 billion and R1.2 billion respectively. Further to this is approximately R1.6 billion for the Mponeng life of mine extension and deepening project. This was partially offset by a R0.8 billion decrease for the Kareerand TSF extension as the project comes to an end in FY26.
|
||||||||||||||||||||||||
| Disclosure of Guarantees |
1The guarantees and suretyships mainly relate to Eskom guarantees. 2At 30 June 2025, R257 million (2024: R217 million) has been pledged as collateral for environmental guarantees in favour of certain financial institutions. Refer to note 15.
|
||||||||||||||||||||||||