Remaining Unsatisfied Performance Obligations
9 Months Ended
Sep. 30, 2025
Remaining Unsatisfied Performance Obligations  
Remaining Unsatisfied Performance Obligations

Note 8. Remaining Unsatisfied Performance Obligations

Remaining Unsatisfied Performance Obligations (“RUPO”) consists of two components: (1) unearned revenue and (2) contracts that are awarded but not started. Unearned revenue includes the revenue we expect to record in the future on in-progress contracts, including 100% of our consolidated joint venture contracts and our proportionate share of unconsolidated joint venture contracts. Contracts that are awarded, but not yet started, are included in RUPO once a contract has been fully executed and/or we have received a formal “Notice to Proceed” from the project owner.

​

Although RUPO reflects business that we consider to be firm, deferrals, cancellations and/or scope adjustments may occur. RUPO is adjusted to reflect any known project cancellations, revisions to project scope and cost, foreign currency exchange fluctuations and project deferrals, as appropriate.

​

Fixed price contracts, particularly with federal, state and local government customers, are expected to continue to represent a majority of our total RUPO.

​

As of September 30, 2025, Southland had $2.3 billion of RUPO. The Company expects to recognize approximately 39% of its RUPO as revenue during the next twelve months, and the balance thereafter.

​