| Schedule of Property, Plant and Equipment |
The following table presents the components of property, plant and equipment: | | | | | | | | | | | | | | | | | | | December 31, 2025 | | May 25, 2025 | | May 26, 2024 | | Land and land improvements | $ | 3,491 | | | $ | 3,739 | | | $ | 3,739 | | | Buildings and building improvements | 82,021 | | | 63,732 | | | 62,874 | | | Machinery and equipment | 82,139 | | | 61,183 | | | 61,013 | | | Computer equipment and software | 7,852 | | | 8,373 | | | 8,290 | | | Furniture and fixtures | 1,422 | | | 1,635 | | | 1,631 | | | Construction in process | 4,545 | | | 42,231 | | | 39,151 | | Idle construction in process | 4,994 | | | 5,525 | | | 22,801 | | | Property, plant, and equipment, gross | 186,464 | | | 186,418 | | | 199,499 | | Less: accumulated depreciation | (59,160) | | | (57,412) | | | (50,334) | | | Property, plant, and equipment, net | $ | 127,304 | | | $ | 129,006 | | | $ | 149,165 | |
|