v3.26.1
ASSET ACQUISITION AND REALLOCATION OF EQUITY INTEREST (Details)
$ in Thousands
12 Months Ended
Dec. 30, 2025
MW
Jul. 14, 2025
MW
shares
Dec. 09, 2024
USD ($)
item
shares
Dec. 03, 2024
MW
Dec. 31, 2025
USD ($)
MW
Dec. 31, 2024
USD ($)
ASSET ACQUISITION AND REALLOCATION OF EQUITY INTEREST            
Non-controlling interests         $ 496 $ 9,887
Remeasurement of unfavorable contract         2,225  
Remeasurement of intangible assets         $ 1,405  
Alpha Data Center PLC ("Alpha")            
ASSET ACQUISITION AND REALLOCATION OF EQUITY INTEREST            
Maximum planned power capacity in megawatts | MW       100    
Consideration for right of electrical power capacity     $ 0      
Term of right of electrical power     2 years      
Alpha Data Center PLC ("Alpha")            
ASSET ACQUISITION AND REALLOCATION OF EQUITY INTEREST            
Percentage of equity interest     51.00% 51.00% 95.00%  
Ownership percentage     49.00%      
Non-controlling interests         $ 8,788  
Acquisition of Guanghan Data Center Co., Ltd.            
ASSET ACQUISITION AND REALLOCATION OF EQUITY INTEREST            
Units of mining machines     16,628      
Consideration transferred     $ 2,265      
Total power capacity of data centers | MW   55        
Term of exclusive usage rights to the mining machines given to sellers     2 years      
Acquisition of Guanghan Data Center Co., Ltd. | USDT            
ASSET ACQUISITION AND REALLOCATION OF EQUITY INTEREST            
Consideration transferred in the form of cryptocurrency | item     2,265,000      
Acquisition of Guanghan Data Center Co., Ltd. | Class A ordinary shares            
ASSET ACQUISITION AND REALLOCATION OF EQUITY INTEREST            
Number of shares issued for acquisition | shares   45,278,600 369,031,800      
Alpha Data Center PLC ("Alpha")            
ASSET ACQUISITION AND REALLOCATION OF EQUITY INTEREST            
Percentage of voting interests acquired 44.00%   51.00%      
Maximum planned power capacity in megawatts | MW 55          
Data center power capacity | MW 45          
Mining data center abandoned operational power capacity | MW         45  
Business Combination, Consideration Transferred, Percentage Of Mining Machines 49.00%          
Alpha Data Center PLC ("Alpha") | Alpha Data Center PLC ("Alpha")            
ASSET ACQUISITION AND REALLOCATION OF EQUITY INTEREST            
Ownership percentage 5.00%