v3.26.1
Schedule of Receivables, Other Receivables and Deposits (Details) - USD ($)
Dec. 31, 2025
Dec. 31, 2024
Dec. 31, 2023
Deferred Costs, Capitalized, Prepaid, and Other Assets Disclosure [Abstract]      
Utility deposit $ 785,600 [1] $ 375,000 $ 375,000
Deposit for the purchase of miners 160,000 397,000
Hosting service in Tennessee data center 23,366
Other sundry deposits 7,881 23,707 2,345
Total $ 816,847 $ 558,707 $ 774,345
[1] The Company increased capacity from 10MM to 22MW. Thus, Duff and Memphis site increased electricity deposit by $125,000 and $285,600, respectively.