Data Center Operations

Note 3. Data Center Operations

In 2025, the Company began leveraging its core competencies in power optimization, strategic land acquisition, engineering design, and construction execution to actively pursue opportunities to develop and monetize portions of its existing facilities and power pipeline through the provision of data center leasing services.

AMD Lease

In January 2026, the Company entered into the AMD Lease, a long-term data center lease agreement with AMD, a leading innovator in high-performance computing, graphics, and visualization technologies, at the Rockdale Facility. The AMD Lease includes an initial deployment of 25 MW of critical IT load capacity to be delivered in phases beginning with 5 MW of critical IT load capacity that was delivered in January 2026 and a remaining 20 MW that is anticipated to be delivered in May 2026. The AMD Lease carries a term of 10 years, with three five-year extension options. The AMD Lease included an expansion option for an additional 75 MW of critical IT load capacity and a right of first refusal for another 100 MW, totaling 200 MW.

​

In April 2026, the Company entered into an amendment to the AMD Lease (the “AMD Lease Amendment”) to exercise a portion of the existing expansion option in the AMD Lease to provide an additional deployment of 25 MW of critical IT load capacity. Under the AMD Lease Amendment, AMD holds a remaining balance of 50 MW of reserved critical IT load capacity under the existing

expansion option. The AMD Lease Amendment also grants AMD a conditional, first-priority right to lease up to an additional 100 MW of critical IT load capacity, exercisable in increments of not less than 50 MW. If both the remaining 50 MW of reserved capacity under the existing expansion option and the additional 100 MW option are fully exercised, AMD’s total leased capacity at the Rockdale Facility would increase to 200 MW. This conditional, first-priority right replaces the right of first refusal for an additional 100 MW previously granted to AMD in the AMD Lease.

​

Under the AMD Lease, power is provided to AMD at pass-through rates and recognized as variable lease revenue in the same period the related expenses are incurred.

​

The Company is also required to provide tenant fit-out services to AMD. Tenant fit-out services include the procurement and installation of customer-specific equipment provided in accordance with the terms of the agreement. All associated costs incurred by the Company plus a margin, will be reimbursable and paid by AMD. For the three months ended March 31, 2026, the Company incurred total costs of $30.7 million.

​

The following table presents the components of the Company’s Data Center revenue for the three months ended March 31, 2026:

​

​

​

​

​

Operating lease revenue

​

$

900

Variable lease revenue, including power reimbursement

​

​

27

Tenant fit-out reimbursement revenue

​

​

32,223

Total Data Center revenue

​

$

33,150

​

The following table presents the Company’s future minimum operating lease payments to be received as of March 31, 2026. The table only includes base rent and excludes reimbursements and variable lease components:

​

​

​

​

​

Remainder of 2026

​

$

18,450

2027

​

 

27,540

2028

​

​

28,366

2029

​

 

29,218

2030

​

 

30,095

Thereafter

​

 

176,306

Total undiscounted lease payments

​

$

309,975

​