Acquisitions and Dispositions
6 Months Ended
Jun. 30, 2026
Business Combination, Asset Acquisition, Transaction between Entities under Common Control, and Joint Venture Formation [Abstract]  
Acquisitions and Dispositions ACQUISITIONS AND DISPOSITIONS
See Note 15 to the financial statements in Item 8 of the Form 10-K for additional information.
Southern Power
Construction Projects
During the six months ended June 30, 2026, Southern Power completed construction of and placed in service the 200-MW first phase and continued construction of the 180-MW second phase and 132-MW third phase of the Millers Branch solar facility. At June 30, 2026, the total cost of construction incurred for the Millers Branch project
was $718 million, of which $408 million remains in CWIP. The ultimate outcome of these matters cannot be determined at this time.
Project
Facility
Resource
Approximate
Nameplate Capacity
(MW)
LocationActual/Projected
COD
PPA
Contract
Period
Projects Under Construction at June 30, 2026
Millers Branch
Phase IISolar180Haskell County, TXThird quarter 202615 years
Phase III
Solar
132Haskell County, TX
Fourth quarter 2026
15 years
Projects Completed During the Six Months Ended June 30, 2026
Millers Branch
Phase I
Solar200Haskell County, TXFebruary 202620 years
Wind Repowering Projects
During the six months ended June 30, 2026, Southern Power continued the development projects to repower the Kay, Grant, Grant Plains, Wake, and Bethel wind facilities. At June 30, 2026, the total cost of construction incurred related to the projects was $598 million, of which $409 million remains in CWIP. The repowered output of the facilities is contracted under new and amended PPAs. The ultimate outcome of these matters cannot be determined at this time.
Project FacilityResource
Approximate Nameplate
Capacity
(MW)
LocationActual/Projected
Completion Date
Projects Under Construction at June 30, 2026
Kay(a)
Wind
200
Kay County, OK
   July 2026(b)
Grant
Wind
152
Grant County, OK
Fourth quarter 2026
Grant Plains
Wind
147
Grant County, OK
Fourth quarter 2026
Wake
Wind
257
Crosby & Floyd Counties, TX
Second quarter 2027
BethelWind276Castro County, TXThird quarter 2027
(a)The facility has a total capacity of 299 MWs, of which 200 MWs was projected to be repowered and is contracted under a PPA.
(b)During the first six months of 2026 and subsequent to June 30, 2026, Southern Power placed all 200 MWs of repowered capacity in service.
Natural Gas Turbine Upgrade Projects
In the first quarter 2026, Southern Power committed to projects to upgrade certain turbines at its existing Franklin and Wansley natural gas facilities, located in Lee County, Alabama and Heard County, Georgia, respectively. The upgrades are projected to add up to 400 MWs of incremental capacity, with commercial operations projected to begin between the second quarter 2029 and the fourth quarter 2030. At June 30, 2026, the total cost of construction incurred related to the projects was $82 million, which is included in CWIP. The ultimate outcome of these matters cannot be determined at this time.